We updated lighting of an assembly hall for MÁV train company in Dunaújváros, Hungary

When starting the project by checking the existing lighting it came out that the system is worst than we expacted, whats more, it was dangerous for working at one of MÁV's assembly halls.

We start planning with redrawing the paths of the fixtures to follow the maintenance bridges for getting the most optimal solution. Regarding that we calculated with the worst scenario (as shown below) when all the tracks in the hall are full of train cars. We ended up doubleing the number of th existing fixtures.

máv_dunaujvaros_dmlhungary_1

máv_dunaujvaros_dmlhungary_2

 

We used high bay fixtures and floodlights as well. Overall lighting is coverd with DMLS HB-21 induction from above and DMLS RF-006 induction from the sides of the hall.

 

Reference images: