Light reconsctruction of the Pipacsvirág elementary School in Telki was one of DML Hungary Ltd.'s major projects. Despite the scale of the building and the huge amount of fixtures needed to be replaced the project was finished within only 10 days. Big resoult with "small" effort as one could say.

Cionditions of work, the mood of the pupils and teachers, or the overall moral of the whole community became better thanks to the improvement of the light environment and light intensity. we can say the Eco-footprint of the institute became more accettable, which has to be the main goal of every similar project regarding the upgrade of lighting in such an institute or every other smaller project as well.

DMLS and LED technologies were both parts of this huge project in the following areas:

  • classrooms
  • library
  • offices
  • reception
  • social areas
  • gym
  • corridors
  • bathrooms
  • diner
  • technical rooms

Our colleagues installed no less than 603 pieces of fixtures (20 different types) and the result is a mindblowing 61,43% savings on energy.

Very important to mention that this project was financed by ESCO construction complemented with operation services.
Over the 4-5 years of lifeterm on LED and DMLS fixtures, our ESCO financing partner contracted for another plus 5 years on operation services which means a longterm safe and economic lighting environment without any extra charges.

This way the investor's own resource was 0%, and the garantee of the profitable undetaking is the 60% energy saving.

A very tense work pace was expected: construction works had to be well coordinated and planned regarding the fact that the well sheduled school time must had been held strictly as teaching and special classes were countinuous.

But we finally managed to finish the work just in time with remarkable results which are highlighted in the table above:

Gym
Before reconstruction – 2016.10.03.
measuring point light intensity (lux) measuring point light intensity (lux)

average light intensity (lux)

1 80 9 201 197
2 84 10 278
3 75 11 234
4 91 12 247
5 122 13 279
6 141 14 341
7 217 15 300
8 139 16 318
After reconstruction – 2016.12.28.
measuring point light intensity (lux) measuring point light intensity(lux) average light intensity (lux)
1 239 9 351 350
2 297 10 376
3 342 11 412
4 332 12 394
5 379 13 374
6 387 14 359
7 381 15 318
8 372 16 291
Ground floor - western corridor
Before reconstruction – 2016.10.03.
measuring point  light intensity (lux)  measuring point   light intensity (lux)   average light intensity (lux)  
1 75 5 198 107
2 80 6 131
3 61 7 88
4 129 8 94
After reconstruction– 2016.12.28.
measuring point   light intensity (lux)    measuring point   light intensity (lux)    average light intensity (lux)  
1 300 5 317 225
2 141 6 147
3 311 7 312
4 139 8 131
Classroom
Before reconstruction – 2016.10.03.
measuring point    light intensity (lux)   measuring point    light intensity (lux)   average light intensity (lux)    
1 351 7 297 523
2 679 8 502
3 317 9 513
4 742 10 746
5 764 11 504
6 518 12 346
After reconstruction– 2016.12.28.
measuring point     light intensity (lux)    measuring point     light intensity (lux)    average light intensity (lux)    
1 554 7 542 742
2 872 8 813
3 583 9 732
4 938 10 945
5 924 11 730
6 691 12 576

Reference images